Work In Progress


MasterTag Finishing & Fullfillment Center Expansion
Montague, MI

  • GENERAL CONTRACTOR
  • Anticipated Project Completion - August 2010
  • Status - 15% Complete
  • Contract -$1,800,000

Montague Area Public Schools - High School & NBC Middle School - BP#4
Montague, MI

  • GENERAL TRADES
  • Anticipated Project Completion - August 2010
  • Status - 0% Complete
  • Contract -$155,000

Ravenna Public Schools - Early Childhood Center
Ravenna, MI

  • GENERAL TRADES
  • Anticipated Project Completion - October 2010
  • Status - 0% Complete
  • Contract -$119,000

New Buffalo Middle School & High School
New Buffalo, MI

  • CASEWORK
  • Anticipated Project Completion - November 2010
  • Status - 0% Complete
  • Contract -$75,000

Hillcrest Nursing & Rehabilitation Community
North Muskegon, MI

  • GENERAL CONTRACTOR
  • Anticipated Project Completion - May 2010
  • Status - 75% Complete
  • Contract - $166,000

Arcadia Highlands - www.arcadiahighlands.com
Arcadia, MI

  • GENERAL CONTRACTOR
  • Anticipated Project Completion - N/A
  • Status - Design / Development / Bidding
  • Contract - N/A

Zielinski Residence
Spring Lake, MI

  • GENERAL CONTRACTOR
  • Anticipated Project Completion - June 2010
  • Status - 85% Complete
  • Contract - N/A
WinBerg Construction
8868 Water Street
Montague, MI 49437

All contents © 2007 WinBerg Construction. All rights reserved. Terms of Use
www.imuadev.com
(231) 894 - 8409 Tel
(231) 893 - 1377 Fax
info@winbergconstruction.com

Web Site Developed by Qonverge